Home
About Howell
A Walk Through Time
Demographics
Festivals
The History of Howell
Programs and Policies
News
Government
Mayor
City Council
Council Meeting Dates
City Manager
Boards & Commissions
Board of Review
Brownfield Redevelopment
Building Authority
Cable TV Commission
Capital Improvement Rate Advisory
Downtown Development Board
Econonic Develop
Officers Compensation
Planning Commission
Rec Commission/Authority
Tax Increment Finance Authority
Zoning Board of Appeals
City Ordinances
Citizen's Academy
Assessing
Beach at Howell City Park
Boat Launch
Clerk
Community Development
Engineering
Finance
Human Resources
Information Technology
Parks and Cemetery
Parks
Police
Public Works
Leaf Brush Yard Waste Pickup
Neighborhood Tree Planting
Recycling Program
Waste Water
Waste Water Process
Water Treatment
Water Treatment Process
Calendar
FAQ
Links
Community Groups
Education
Healthcare
Historical
Local Media
Surrounding Communitites
Things to do
Contact Us
Directory



 

May 4th, 2012 at 11:03 am

Progress continues on the Howell Multi Year Street Project Year 3.

 

5/10/12 Storm sewer at the George/Washington Intersection

5/10/12 - 5/11/12   Grading on Tompkins

5/11/12 Water Service on George

Week of 5/14/2012 -

           Santitary Sewer work on Washington continues

           Cutting grade on George to prepare for road

Week of 5/28/12 - Pulverize/remove asphalt on Isbell (south of the   tracks) and Center Street 

 

Week of May 14th they will begin with bituminous paving(asphalt) on

Swann Court, moving onto the west end of Maple, then to S Tompkins.

 

NOTE - Driveway installation will be done during the first layer of asphalt

 

Emails have been sent to residents that are affected, if they provide email addresses to us.

 

REMEMBER - THIS SCHEDULE CAN ALTER DUE TO ANY UNFORESEEN WEATHER.

 

Any questions or comments, please do not hesitate to contact our office 546-3861.

 

Thanks again

 

 

Posted in
by
Views:
40
April 30th, 2012 at 3:05 pm

Weather conditions can and will delay any construction project. 

 

The contractors work diligently to work through the weather, but in cases of extreme rain, or weather conditions, the contractors might need to leave the site.

 

Please always watch the website for updates as they occur.

 

Thanks for your patience during this construction season.

 

Posted in
by
Views:
37
March 9th, 2012 at 9:23 am

The current construction project that is occuring S. of Grand River, and W. of Michigan Ave. involves several utility improvements, including water main upgrades.  These will help provide reliable water and sewer service for the entire neighborhood.  Unfortunately at times it becomes necessary to flush hydrants and turn valves which may stir up iron, causing some residents to have orange water.  The water is perfectly safe for use.  Please run your faucets until it clears up before  you use it, this should take no more than 15 minutes. 

If it continues to happen or you need assistance, please contact the dps department at 517-546-7510.