Progress continues on the Howell Multi Year Street Project Year 3.
5/10/12 Storm sewer at the George/Washington Intersection
5/10/12 - 5/11/12 Grading on Tompkins
5/11/12 Water Service on George
Week of 5/14/2012 -
Santitary Sewer work on Washington continues
Cutting grade on George to prepare for road
Week of 5/28/12 - Pulverize/remove asphalt on Isbell (south of the tracks) and Center Street
Week of May 14th they will begin with bituminous paving(asphalt) on
Swann Court, moving onto the west end of Maple, then to S Tompkins.
NOTE - Driveway installation will be done during the first layer of asphalt
Emails have been sent to residents that are affected, if they provide email addresses to us.
REMEMBER - THIS SCHEDULE CAN ALTER DUE TO ANY UNFORESEEN WEATHER.
Any questions or comments, please do not hesitate to contact our office 546-3861.
Thanks again